Client
SRM & Battersea Power Station
Scope
Mechanical, Public Health, BMS and Fire Suppression Basements and Infrastructure
Contract Value
£14m
Duration
November '21 – November '23
Status
Construction
Category
Commercial
Project Description
GBE are employed under a bespoke Battersea developments Trade Contract to undertake the Lead Co-ordination design, and the manufacture, supply, install, test, commission and set to work the Mechanical, Public Health, Building Management System and Fire Suppression Services – Basement and Infrastructure, for the development(s) known as Battersea Phase 3B comprising O-1 Residential Building (Core D) and, O-1 Commercial Building.
GBE were responsible for the following systems.
- Chilled-water systems
- Low-temperature hot water systems
- Domestic water systems
- Public health, soil waste & vent, rainwater/stormwater collection and pumped drainage including the drainage from the stacks to bathroom pods and utility cupboards within the apartments.
- Water treatment systems
- Air conditioning and ventilation systems, (excluding car park smoke extract and apartment AOV systems and firefighting lift lobby smoke ventilation in the commercial building) including other smoke extract systems.
- Split A/C / DX systems serving rooms as detailed on schematic and layout drawings
- Condensate waste from equipment to sanitary collection system
- Thermal insulation and electric trace heating
- Acoustic and anti-vibration requirement
- Pipework expansion and contraction
- Mechanical systems electrical equipment and cabling
- Miscellaneous plant and equipment
- Building Management System including Motor Control Centres
- Sprinkler system including fire pump room and wet risers
- Leak detection and bunds under MER floor
- Utility services connections into apartment utility cupboards and interface design between Trade Contractor works and residential apartment fit out works.
After a full design validation, GBE were able to implement off site manufacturing and prefabrication of the following.
- Residential Corridor Pipework Modules
- Mechanical Riser Pipework and Frames
- Commercial Building HIU & CIU Arrangements
- Basement Plantroom Pump Modules
- LTHW and CHW Pipework
- BCWS Stainless Steel Pipework