DeVere Gardens

Mechanical shell and core installation serving 97no luxury new build apartment block in Kensington.
Full plant modularisation including the provision of riser service frames and roof gantry steelwork.

 

Contract value £3,100,000

 

Images of part of GBE's installation, and impression of the completed building

 

Exterior visualisation
Construction underway in GBE
Module assembled in GBE Fabrications facility
Completed module ready for transport
Plant loaded inside GBE fabrication facility
Gantrywork lift into the blue
Gantry lifted into position
Gantry module ready to install
Gantry module ready to install
Lifting to upright position
Riser assembly upright and ready to lift
Lift underway
Risers installation
Platform gantry in position